One of our outstanding advantages is our high passing rate, which has reached 99%, and much higher than the average pass rate among our peers. Our high passing rate explains why we are the top PK0-004 prep guide in our industry. One point does farm work one point harvest, depending on strength speech! The source of our confidence is our wonderful PK0-004 exam questions. Passing the exam won’t be a problem as long as you keep practice with our PK0-004 Study Materials about 20 to 30 hours. Considered many of the candidates are too busy to review, our experts designed the PK0-004 question dumps in accord with actual examination questions, which would help you pass the exam with high proficiency.

CompTIA PK0-004 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Create effective communication, change management and transition plans
  • Create project staffing and quality management plans
Topic 2
  • Initiate a project, including creating project plans
  • stakeholder strategies, and scope statement
Topic 3
  • Develop a work breakdown structure and activity lists
  • Identify the fundamentals of project management
Topic 4
  • Create a risk management plan, perform risk analysis, and develop a risk response plan
  • Perform project closure activities
Topic 5
  • Develop a project schedule, identify the critical path and costs
  • Monitor and control project performance, constraints, risks and procurements

CompTIA PK0-004 is a required exam for earning the CompTIA Project+ certification. The test is designed to equip the candidates with the skills needed to manage a project’s lifecycle, manage the stakeholders and resources, ensure clear communications, and keep project documentation. Those specialists who pass this exam will be able to understand the basic concepts required to manage small- to medium-sized projects successfully.

>> PK0-004 New Guide Files <<

Best PK0-004 Preparation Materials | Knowledge PK0-004 Points

Knowledge is defined as intangible asset that can offer valuable reward in future, so never give up on it and our PK0-004 exam preparation can offer enough knowledge to cope with the exam effectively. To satisfy the needs of exam candidates, our experts wrote our PK0-004 practice materials with perfect arrangement and scientific compilation of messages, so you do not need to study other numerous PK0-004 study guide to find the perfect one anymore.

Recommended Experience

The CompTIA PK0-004 exam is aimed at a wide range of professionals from the entry-level specialists who are new to the project management industry to the qualified project managers who want to improve their skills, upgrade their organizational title, enhance their income, or meet the certification requirements of their enterprise.

There are no official requirements for the CompTIA PK0-004 exam. However, the applicants are recommended to have at least one year of working experience in managing or participating in small- to medium-scale projects or undertake equivalent education.

CompTIA Project+ Certification Exam Sample Questions (Q788-Q793):

NEW QUESTION # 788
A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up to the meeting. Which of the following MOST likely describes why this occurring?

  • A. Language barriers prevent team members from participating.
  • B. The meeting is occurring too frequently.
  • C. There is no rapport between the team members and the project manager.
  • D. The time zone in the one country is outside of working hours.

Answer: D


NEW QUESTION # 789
Which of the following documents need to be updated as events occur during a project?
(Select TWO).

  • A. Meeting minutes
  • B. Status report
  • C. Issue log
  • D. Change request
  • E. Risk register

Answer: A,B


NEW QUESTION # 790
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days,
and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15,
which of the following is the anticipated start date for Task D?

  • A. December 19
  • B. December 20
  • C. December 22
  • D. December 18
  • E. December 21

Answer: D


NEW QUESTION # 791
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

  • A. Project team members
  • B. Project manager
  • C. Project scheduler
  • D. Project sponsor

Answer: B

Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82


NEW QUESTION # 792
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?

  • A. Schedule
  • B. Scope
  • C. Time
  • D. Cost

Answer: D


NEW QUESTION # 793
......

Best PK0-004 Preparation Materials: https://www.prepawaytest.com/CompTIA/PK0-004-practice-exam-dumps.html